Scope
of Work:
Installation
and Commissioning of Electrical
BOP, including:
- Installation and Commissioning of Common MV Switchgear
- Installation and Commissioning of LV Switchgears
- Installation and Pre-commissioning of Control Panels
- Calibration, Installation and commissioning of Field Instruments and Hook-up Material
- MV, LV and I&C Cable pulling and Termination (160 Km)
- Installation of Cable Ladder, Tray and accessories
- Installation and Commissioning of Heat Tracing system
- Installation and commissioning of Cathodic Protection system
- Installation and Commissioning of Fire Alarm system
- Installation and
Commissioning of Telephone, Paging, Fire Telephone and LAN systems
- Installation and
Commissioning of Emergency Diesel Generators (2 Sets)
- Supervision on Commissioning for Utility Systems (Fuel System, HVAC, Fire Fighting, Raw Water, Aux. Cooling, Aux. Boiler, Foam, etc.)